SETEK / ENGINEERING METHODOLOGY

From requirement to ready for operation.

A documented, collaborative delivery method for modular data center and critical infrastructure projects.

RFI › BoD › DESIGN › REVIEW › FAT › SAT / IST
01

RFI

Requirements & site information

Collect IT workloads, GPU/server types, rack plans, electrical connection, cooling boundaries, location constraints, compliance requirements and growth expectations.

Output: RFI response register and missing-input list
02

BoD

Basis of Design

Establish design assumptions, target capacities, operating temperatures, redundancy, maintainability, package boundaries and acceptance criteria.

Output: Reviewed Basis of Design
03

DESIGN

Preliminary engineering & BOM

Coordinate layouts, electrical single-line design, preliminary cooling flow diagrams, structural interfaces, service clearances, preliminary equipment list and budgetary scope.

Output: Preliminary drawings, scope matrix and BOM
04

REVIEW

Interface & design review

Review design disciplines and responsibilities across supplier, factory integrator and site owner; assess power, liquid loops, heat rejection, transport, seismic constraints and site interfaces.

Output: Interface register, risk list and controlled revisions
05

FAT

Factory Acceptance Test

Define and witness the agreed functional and load tests, control logic, alarm sequences, electrical checks and cooling/leak tests before shipment.

Output: FAT protocol, test report and open-items list
06

SAT / IST

Site acceptance & operational handover

Verify installation and connections, commissioning and integrated tests. Complete acceptance records, as-built drawings, O&M documents and operator orientation.

Output: SAT / IST evidence and handover file

Requirements first. Validated delivery follows.

Engineering calculations, scope, test procedures, certifications and lead times are defined per project, with the responsible parties.

Discuss your project ↗

SETEK / MÜHENDİSLİK METODOLOJİSİ

İhtiyaçtan işletmeye hazır sisteme.

Modüler veri merkezi ve kritik altyapı projelerini gereksinimden teslimata taşıyan, kayıtlı ve iş birliğine dayalı çalışma yöntemi.

RFI › BoD › DESIGN › REVIEW › FAT › SAT / IST
01

RFI

İhtiyaç ve saha bilgilerinin toplanması

IT iş yükü, GPU/sunucu tipleri, kabinet planı, elektrik bağlantısı, soğutma sınırları, saha kısıtları, uyulacak standartlar ve büyüme beklentileri toplanır.

Çıktı: RFI yanıt tablosu ve eksik bilgi listesi
02

BoD

Tasarım esaslarının oluşturulması

Tasarım varsayımları, hedef kapasite, çalışma sıcaklıkları, yedeklilik, bakım koşulları, paket sorumlulukları ve kabul kriterleri tanımlanır.

Çıktı: İncelenmiş Tasarım Esasları (BoD)
03

DESIGN

Ön mühendislik ve BOM

Yerleşimler, elektrik tek hat yaklaşımı, soğutma akış diyagramları, yapısal arayüzler, servis boşlukları, ön malzeme listesi ve bütçe kapsamı koordine edilir.

Çıktı: Ön çizimler, kapsam matrisi ve BOM
04

REVIEW

Arayüz ve tasarım incelemesi

Tedarikçi, fabrika entegratörü ve saha taraflarının sorumlulukları; güç, sıvı devreleri, ısı atımı, nakliye, sismik koşullar ve saha bağlantıları üzerinden birlikte incelenir.

Çıktı: Arayüz matrisi, risk listesi ve çizim revizyonları
05

FAT

Fabrika kabul testi

Sevkiyat öncesinde üzerinde mutabık kalınan fonksiyon ve yük testleri, kontrol senaryoları, alarmlar, elektrik kontrolleri ve soğutma/sızıntı testleri uygulanır.

Çıktı: FAT protokolü, test raporu ve açık maddeler
06

SAT / IST

Saha kabulü ve işletmeye teslim

Kurulum ve bağlantılar, devreye alma ve entegre sistem testleri doğrulanır. Kabul kayıtları, son durum çizimleri, işletme-bakım dosyaları ve operatör bilgilendirmesi tamamlanır.

Çıktı: SAT / IST raporu ve teslim dosyası

Önce ihtiyaçlar. Ardından doğrulanmış teslim.

Mühendislik hesapları, kapsam, test prosedürleri, sertifikasyon ve teslim süreleri projeye özel olarak sorumlu taraflarla belirlenir.

Projenizi görüşelim ↗

SETEK / MÉTHODOLOGIE D’INGÉNIERIE

Des exigences à la mise en service.

Une démarche collaborative et documentée pour concevoir, vérifier et livrer des infrastructures modulaires critiques.

RFI › BoD › DESIGN › REVIEW › FAT › SAT / IST
01

RFI

Besoins et données du site

Recueillir la charge informatique, les baies, l’alimentation, le refroidissement, les contraintes du site et les normes pertinentes.

Livrable: Registre RFI et liste des données manquantes
02

BoD

Base de conception

Définir les hypothèses, capacités, températures, redondance, maintenance, interfaces et critères de réception.

Livrable: Base de conception examinée
03

DESIGN

Ingénierie préliminaire et nomenclature

Coordonner plans, schéma électrique, circuits thermiques, interfaces structurelles, accès de maintenance et liste des équipements.

Livrable: Plans préliminaires, matrice de périmètre et BOM
04

REVIEW

Revue des interfaces et du design

Examiner les responsabilités du fabricant, de l’intégrateur et du site pour l’électricité, le refroidissement, le transport et les contraintes sismiques.

Livrable: Registre des interfaces, risques et révisions
05

FAT

Réception en usine

Réaliser les essais convenus de fonctionnement, charge, contrôle, alarmes, électricité et refroidissement avant expédition.

Livrable: Protocole FAT, résultats et réserves
06

SAT / IST

Réception sur site et remise

Vérifier installation, raccordements, mise en service et essais intégrés; compléter les plans finaux, documents O&M et formation.

Livrable: Rapports SAT / IST et dossier de transfert

Les besoins d’abord. La livraison validée ensuite.

Les calculs, le périmètre, les essais, les certifications et les délais sont définis pour chaque projet.

Parler de votre projet ↗

SETEK / منهجية الهندسة

من المتطلبات إلى جاهزية التشغيل.

عملية عمل موثقة وتعاونية لتصميم والتحقق من وتسليم مراكز البيانات المعيارية والبنية التحتية الحيوية.

RFI › BoD › DESIGN › REVIEW › FAT › SAT / IST
01

RFI

المتطلبات وبيانات الموقع

جمع أحمال الخوادم والخزائن والطاقة والتبريد وقيود الموقع والمتطلبات التنظيمية وخطط التوسع.

المخرجات: سجل طلب المعلومات وقائمة النواقص
02

BoD

أسس التصميم

تحديد الافتراضات والقدرات ودرجات الحرارة والتكرار والصيانة والمسؤوليات ومعايير القبول.

المخرجات: وثيقة أسس التصميم المعتمدة
03

DESIGN

الهندسة الأولية وقائمة المواد

تنسيق التخطيط الكهربائي والحراري والإنشائي وممرات الصيانة وقائمة المعدات والتكلفة التقديرية.

المخرجات: الرسومات الأولية ومصفوفة النطاق وقائمة المواد
04

REVIEW

مراجعة الواجهات والتصميم

مراجعة مسؤوليات المصنع والمكامل والموقع والطاقة والتبريد والنقل والقيود الزلزالية.

المخرجات: سجل الواجهات والمخاطر ومراجعات التصميم
05

FAT

اختبار القبول بالمصنع

تنفيذ الاختبارات المتفق عليها للوظائف والأحمال والتحكم والإنذارات والكهرباء والتبريد قبل الشحن.

المخرجات: بروتوكول وتقرير FAT والملاحظات
06

SAT / IST

القبول بالموقع والتسليم

التحقق من التركيب والتوصيلات والتشغيل والاختبارات المتكاملة وإكمال وثائق التشغيل والصيانة والتدريب.

المخرجات: تقارير SAT / IST وملف التسليم

المتطلبات أولاً، ثم التسليم المتحقق منه.

تحدد الحسابات والنطاق والاختبارات والشهادات والمواعيد لكل مشروع مع الجهات المسؤولة.

ناقش مشروعك ↗